Forecasts

AI campus power claims need a docket check.

Our analyst team turned the forecast into a 31-page diligence dossier: verify or refute whether announced AI campuses can actually energize.

The broad insight, data-center power is scarce, is now public. The sharper product is more useful: test the exact power story attached to a site before capital treats it as real.

Bad pitch

Power-secured AI campuses win.

Better pitch

Prove whether a claimed power-secured campus survives primary-source diligence.

Hard label rule

No row can be called power secured unless primary or official sources verify MW, counterparty/offtake, interconnection or behind-the-meter path, and permit/regulatory status.

leadsource verifiedcontesteddemotedinterconnection risk

Docket spine

These are the public record surfaces that make the product concrete. The work starts where the press release stops.

primary verified

RM26-4-000

FERC large-load interconnection ANOPR, including data centers and co-located/flexible load.

Watch for Commission action by end-June 2026.

primary verified

EL25-49 / AD24-11 / EL25-20

PJM co-located load rules, behind-the-meter netting, transmission service, and rate design.

Track compliance and paper-hearing replacement-rate issues.

contested

ER24-2172

PJM/Susquehanna/Talen/Amazon ISA amendment; FERC rejected amendments on 2024-11-01.

Watch appellate review and generic PJM co-location dockets.

primary verified

ER26-1088

PJM 30-day compliance filing from EL25-49; FERC accepted in part and rejected in part.

Track further compliance after the 2026-04-16 order.

pending

ER26-1479

PJM 60-day co-located load tariff revisions filed 2026-02-23.

Await FERC merits order.

Sample rows

The sample set already has one crucial correction: Talen/Amazon is not clean proof. It is the flagship contested row in a 12-row project ledger.

PJM, Pennsylvania

AWS / Talen Susquehanna data campus

contested
Verified capacity
Large co-located load tied to Susquehanna nuclear; larger multi-phase claims stay live but not clean.
Why it matters
Core refutation case: commercial story exists, but FERC rejected the ISA amendment.
Next check
Pull ER24-2172, related appeals, and later PJM/FERC filings before using any MW claim.
PJM, Pennsylvania

Constellation / Microsoft Crane Clean Energy Center

restart case
Verified capacity
835 MW company/DOE restart figure.
Why it matters
Nuclear restart and PPA case tied to Microsoft data-center power matching in PJM.
Next check
Track NRC restart/license approvals and PJM deliverability materials.
PJM, Pennsylvania

Google / Brookfield Holtwood + Safe Harbor hydro

framework
Verified capacity
670 MW initial; up to 3,000 MW framework.
Why it matters
Dispatchable hydro procurement for Google PJM operations.
Next check
Pull FERC hydro relicensing dockets, especially Safe Harbor No. 1025.
PJM, Pennsylvania

Homer City Energy Campus

official lead
Verified capacity
4.4-4.5 GW project claim.
Why it matters
Retired coal site converted into gas-powered AI/HPC campus.
Next check
Verify PA DEP permits, PJM interconnection, and tenant energy service agreements.
PJM, Ohio

Amazon / AES Ohio data center

RTO planning
Verified capacity
65 MW at COD; 480 MW by end of Phase I.
Why it matters
Named 345 kV service request with dated ramp schedule.
Next check
Pull AES/PUCO electric service agreement and network upgrade costs.
PJM, Virginia

Dominion Culpeper Tech Zone campuses

utility filing
Verified capacity
188 MW by 2028; 1,164 MW by 2034 aggregate.
Why it matters
Three named campuses driving 230 kV buildout and useful public load evidence.
Next check
Track SCC case status, per-campus MW split, and county approvals.

10-business-day AI Campus Power-Claim Diligence sprint

For a buyer-provided asset list, docket, site, or LOI. The output is a memo-ready call on what to reserve, diligence, monitor, or kill.

Deliverables

  • Five to twelve verified or demoted site rows.
  • One refuted lead, included by design.
  • Time-to-energize risk table and watchlist.
  • Action memo: reserve, avoid, diligence, monitor, or kill.
First buyer

Infrastructure investors and lenders

Use the sprint before underwriting a campus, loan, power JV, or land transaction.

High pain

Municipalities and landowners

Separate a credible powered-campus proposal from a press-release-deep promise.

Credibility wedge

Smaller developers

Use a primary-source dossier to prove a site is more real than larger announced competitors.

Partner screen

Power developers

Find which AI-campus counterparties have a real path through interconnection and permits.

Work with us

Point the engine at your mandate

The chat gives you our standing read in seconds. A commission points the whole research team and the leak-free engine at one question you actually trade on: where the binding constraint sits, whether it is already priced, and the dated signal to watch.

Built for funds and macro desks who want the call before it is consensus. You get the full reasoning and the line that would prove it wrong, so you can size it yourself.

Try the chat first →
Thesis
A dated thesis, not a take
One sub-industry, the binding constraint named, a probability with an interval, and the date it resolves.
Evidence
The data layer behind it
Research, patents, trade flows, and a live price channel, so the call rests on a constraint you can actually measure.
Watch
A kill-criterion you can watch
Every call names what would make it wrong and the signal to watch for it, so you can track the position as it plays out.
Close

Work with us

Tell us what you want the engine pointed at. We read every note ourselves and reply to set up a call with the ones we can move on. Or email [email protected].

Got it. Now pick a time.

Your note is in. Grab a 30-minute call below, or we will reply from [email protected].

Something went wrong while submitting the form.
close