Headline or lead exists, but public records are not strong enough for underwriting.
Time-to-Energize Truth
A source-grade ledger for separating powered AI campuses from capacity announcements still waiting on interconnection, permit, and service evidence.
Rejection criteria make the ledger useful.
A row is not power-secured unless MW, counterparty, power path, tariff or interconnection treatment, permits, and commissioning evidence survive official review.
Official or public sources conflict, or a critical gate remains unresolved.
A credible source supports part of the claim, but official records still determine underwriting status.
Receipts are evidence, not endorsement.
Each project row carries receipts, but a receipt does not promote the claim by itself. Status changes only when official records close the open gate.
Named project ledger
Each row carries source tier, status, demotion reason, next docket or watch date, and the buyer action it changes.
Amazon / Dominion North Anna SMR
MOU-stage evidence is a watchlist lead, not a project with decision-grade energization proof.
At least 300 MW exploratory.
Tier 4 lead only
MOU lead
Exploration does not yet prove SCC, NRC, design, service, or COD evidence.
2026-09-19Dominion / Amazon SMR exploration
Do not underwrite as power-secured; keep as a watchlist lead.
Fermi America Project Matador
Large headline MW requires unusually strict source handling before buyer use.
11 GW claimed.
Tier 2 official incomplete
headline MW unverified
Anchor tenant, TCEQ/NRC path, gas, cooling, and financing remain public-record gaps.
2026-09-19NRC new-reactor page
Treat as a large lead until official permit, tenant, and financing spine is source-grade.
Homer City Energy Campus
Official site ambition exists, but the full power-secured claim is not decision-grade on current public records.
Up to 4.4-4.5 GW.
Tier 2 official incomplete
visible demotion
Tenant/offtake, PA DEP appeal posture, gas capacity, and interconnection proof remain unresolved.
2026-09-19Pennsylvania DEP project page
Demote from power-secured sample until tenant, permit, gas, and interconnection gates close.
NEO Power Gen
Public meeting notice is a lead, not decision-grade source support.
500 MW proposed.
Tier 4 lead only
public-meeting lead
Formal OPSB filing, offtake, gas/BESS design, emissions, and COD evidence are missing.
2026-09-19OPSB public-information meeting
Keep as a lead until formal filings and source-grade offtake emerge.
AWS / Talen Susquehanna
Commercially real asset and strategic deal, but not clean proof of power-secured campus capacity.
300-480 MW disputed load treatment; broader MW not verified here.
Tier 1 official
contested official asset
Replacement ISA and tariff path, backup service, and cost allocation remain decision-relevant gates.
2026-08-17ER24-2172 and PJM co-location filings
Do not treat as clean power-secured proof until the replacement path is verified.
xAI Southaven / Colossus turbines
Public record supports a live power-permitting controversy, not clean energized-MW proof.
41 turbines; MW not primary-verified here.
Tier 1 official
air permit contested
Air permit, litigation, temporary-versus-permanent status, delivered MW, and grid/fuel path remain contested.
2026-09-19MDEQ permit-board minutes
Track as contested behind-the-meter and temporary-to-permanent power row.
AEP Ohio / Bloom / AWS Hilliard fuel cells
Concrete bridge-power pattern, only partially quantified until PUCO and second-site records are extracted.
72.9 MW AWS row; Cologix unknown.
Tier 2 official incomplete
local plus company MW partial
PUCO order, local record, commissioning status, gas supply, and Cologix MW remain unresolved.
2026-09-19AEP Scioto Darby Creek project
Verify PUCO/local record and commissioning status before buyer use.
Amazon / AES Ohio 345-kV service
Cleaner official planning anchor than splashier behind-the-meter claims.
65 MW COD to 480 MW Phase I.
Tier 1 official
RTO planning anchor
Still needs ESA, PUCO/OPSB, network upgrade cost, and COD verification before campus underwriting.
2026-08-20PJM AES Ohio data-center presentation
Use as cleaner official planning anchor; verify service agreement and COD.
Amazon / Energy Northwest / X-energy Cascade
Named strategic SMR path, still pre-license and not buyer-grade firm supply.
320 MW first phase; option for 960 MW.
Tier 3 claim evidence
SMR pre-license
Purchase rights and project ambition need licensing and construction evidence before promotion.
2026-09-19Cascade Advanced Energy Facility
Monitor licensing and construction before treating as firm supply.
Apollo Power Generation
Strong approved gas-plus-storage comparison row, with customer identity still the first buyer question.
350 MW gas plus about 120 MW BESS.
Tier 1 official
BTM approved comparator
Liames/end customer, Ohio EPA, gas pipelines, staged COD, and battery operation still condition underwriting.
2026-09-19Ohio OPSB construction authorization
Use as positive BTM comparator, but condition on customer and permit closure.
Constellation / Microsoft Crane Clean Energy Center
Strong firm-power procurement evidence, not direct proof that a named campus can energize faster.
835 MW nuclear restart.
Tier 2 official incomplete
restart pending NRC
Keep separate from campus energization until NRC restart, PJM deliverability, and physical delivery treatment are clearer.
2026-09-19DOE/NRC restart record
Use as firm-power procurement proof, not behind-the-meter campus proof.
Dominion Culpeper Tech Zone
Strong load-growth proof case; buyer question is which campus has real service rights.
188 MW by 2028 and 1,164 MW by 2034 in SCC materials.
Tier 1 official
utility regulatory, customer unresolved
Aggregate utility planning must be mapped to named campuses, service agreements, and local approvals.
2026-08-20Dominion SCC application
Map delivery points to county approvals and developers.
Google / Brookfield hydro framework
High-quality dispatchable clean-energy procurement evidence, with delivery details still open.
670 MW initial; up to 3,000 MW framework.
Tier 3 claim evidence
framework follow-up
Framework capacity is not the same as verified energizable site MW.
2026-09-19Brookfield / Google hydro framework
Use as clean-power PPA proof with delivery follow-up.
Google / Kairos / TVA Hermes 2
Strategic advanced-nuclear row, not near-term campus power proof.
50 MW first plant; up to 500 MW fleet.
Tier 3 claim evidence
advanced nuclear, long dated
NRC, TVA, construction, and PPA execution remain the actual time-to-energize chain.
2026-09-19Google / Kairos / TVA collaboration
Treat as long-dated strategic energy claim, not near-term campus proof.
Lancium / Crusoe Abilene
Positive delivery comparator, but live initial MW and later staged claims must be split.
200 MW initial; 1.2-2.1 GW company claims.
Tier 3 claim evidence
company verified, records pending
Company claims need ERCOT, TCEQ, onsite gas, and energized-versus-staged evidence before full promotion.
2026-09-19Crusoe Abilene expansion
Split live initial MW from later staged claims.
Meta / Constellation Clinton
Evidence of firm nuclear procurement, not evidence that a specific AI campus can energize faster.
1,121 MW announcement; Clinton reactor lists up to 1,092 MW before uprate context.
Tier 3 claim evidence
nuclear PPA, not campus power
Clean-energy procurement and site energization are different claims.
2026-09-19Constellation PPA announcement
Separate clean-energy procurement from campus energization.
Meta / Vistra Perry, Davis-Besse, Beaver Valley
Useful clean-power and uprate exposure, not proof of new campus commissioning.
2,176 MW existing plus 433 MW uprates.
Tier 3 claim evidence
clean power uprate pending
Uprate approvals, dates, and Meta-linked delivery path still determine buyer-grade value.
2026-09-19Vistra and Meta agreement
Track as clean power and uprate exposure, not proof of new campus COD.
Meta Richland Parish / Entergy
Looks power-secured in narrative, but remains a regulated utility mega-build with approval and cost-allocation risk.
>2 GW compute; 2,260 MW generation package.
Tier 2 official incomplete
regulated buildout approved, pending expansion
LPSC order details, final cost allocation, expansion, gas-unit approval, and service terms still matter.
2026-09-19Entergy / Meta power plan
Do not call online; track approval stage, COD, and expansion filings.
PowerConneX New Albany I/II
Behind-the-meter regulator row with useful public footprint, still conditional on gas and COD.
120 MW plus 216 MW.
Tier 2 official incomplete
regulator BTM data center
OPSB conditions, gas, load tie, and COD still need buyer-grade confirmation.
2026-09-19New Albany natural-gas power page
Track as BTM regulator row; verify gas and COD.
Socrates North/South / Will-Power
One of the cleaner behind-the-meter patterns, but customer identity and gas permits remain gates.
400 MW combined.
Tier 2 official incomplete
BTM counterparty unverified
Counterparty, gas pipelines, conditions, Sidecat/Meta linkage, and COD remain unresolved.
2026-09-19Williams Socrates power facilities
Verify customer, counterparty, gas, air, and COD before underwriting.
Watch calendar
These are the next moments when announced MW can become verified, conditioned, contested, or not decision-grade.
FERC 30-day informational reports
Capture RTO and ISO adequacy logic for new and existing large loads.
NERC computational-load responses
Watch modeling, protection, control, commissioning, SCADA, ramp, reconnect, and ride-through gaps.
FERC 60-day tariff response deadline
Main upgrade or demotion event for large-load tariffs, co-location treatment, behind-the-meter generation, and study rules.
Deficiency, protest, and permit follow-through
Track state/local permits, protests, rehearing requests, and rows that become conditioned or not decision-grade.
Source tier rules
Promotion needs official records. Demotion needs a named failed or unresolved gate. The public claim is judged, not the company.
Tier 1 official
FERC orders, eLibrary, eTariff, RTO tariff filings, state commission orders, signed service or interconnection documents, permits, and NERC alerts.
Tier 2 official incomplete
RTO planning slides, load forecasts, queue data, transmission plans, local board packets, and permit portals.
Tier 3 claim evidence
Company releases, investor decks, SEC filings, customer announcements, EPC or OEM awards.
Tier 4 lead only
Trade press, broker decks, social posts, geospatial hints, and public-meeting leads. Never promote from this tier alone.
Fixed-scope diligence sprint.
For a buyer, the output is a decision: reserve, condition, reprice, monitor, or walk before a false energization date reaches investment committee.
Output
- Five to twelve buyer-specific rows.
- One visible demotion, included by design.
- Source packet and next-source calendar for each row.
- Investment-committee action memo.
Work with us
Put us on one question.
The chat is free and always on. When you need more, we point the whole engine at a single question you trade and come back with a dated forecast: the binding constraint, a probability and interval, whether it's already priced, and when it resolves. You also get the one thing that would prove it wrong, so you can size it and watch it.